1200 MW Natural Gas Fired Combined Cycle PP by Rajanagaram Gas Power Pvt. Ltd.

Tuesday, September 6th, 2011 | Andhra Pradesh

The project involves setting up of unit capacities of 2×1075 MW each in two phases viz. Phase-I 1x1075MW and Phase-II 1×1075 MW. The proposal then was at different location in East Godavari District. The Committee in the said meeting informed the project proponent that the desirable unit configurations could be 2×1200 MW each and they may like to explore the same configuration, to which the project proponent confirmed its intention. The Committee therefore decided that the project proponent shall submit revised Form-I to the Ministry with the changed configuration of 2×1200 MW in lieu of 2×1075
MW. The Committee also in the said meeting observed that the identified site is a fertile agricultural land and as such, could be recommended for setting up of a thermal power plant. The Committee therefore decided that the project proponent shall explore alternative sites and come back again.

The project was considered for environment clearance on Jun 06, 2011

The project was issued environmental clearance on Jul 26, 2011

Contact :

Rajanagaram Gas Power Pvt. Ltd., 6-3-866/2, 3rd Floor,
Above Canara Bank,Begumpet, Hyderabad 500016

Incoming search terms:

  • rajanagaram gas power
  • rajanagaram gas power pvt ltd
  • CNG Based Power Plants coming up in AP
  • Era Infra Engineering Limited 1320 mw ppa
  • rajanagaram gas power pvt ltd power plant mw
  • rajanagaram power project
  • rajanagaram gas power pvt ltd moef jul 26 2011
  • tata gas cycle
  • Rajanagaram Gas Power Private Limited
  • rajanagaram gas power allegation

Download Latest New Projects Report in Excel Format – Feb II, 2012

Tags:

Related ads 1200 MW Natural Gas Fired Combined Cycle PP by Rajanagaram Gas Power Pvt. Ltd.

Expansion of 1000 MW (4x2

The company is planning to take up expansion of 4×250 MW Coal Based

358 MW (ISO Rating) Gas b

The company is planning to take up setting of 358 MW Gas Based

2x10 MW Captive Power Pro

The company is planning to take up setting up 2×10 MW Captive Coal

20 MW Co-generation P.P.

20 MW Co-Generation Plant at village  Lauriya, in West Champaran District , in