2×300 MW Coal based Thermal Power Project in MIDC industrial area at village Tadali by Dhariwal Infrastructure(P) Ltd.

The project involves setting up a 2×300 MW Coal Based Thermal Power Plant in MIDC Industrial Area, at village  Tadali, in District  Chandrapur, in Maharashtra. Land requirement will be 480 acres. Coal requirement will be 11040 TPD and will be sourced from SECL mines. Coal linkage has been obtained from Ministry of Coal. Water requirement of 19.272 mcum per annum will be sourced from Wardha River which flows at a distance of 9.3 km from the plant site. Govt. of Maharashtra has accorded permission for water allocation from Wardha River. A Barrage is proposed to be constructed in Wardha River for uninterrupted water supply.

The project was considered for issuing Environment Clearance  on Oct 13, 2009 and the Environment Clearance  was issued on Dec 4, 2009

Contact :
Dhariwal Infrastructure(P) Ltd.
1008, A-Wing Lokmat Bhawanl,10th Floor, Nagpur 400012 Maharashtra

Switch to our mobile site